SoftBank's Multi-Billion Dollar Turbine Losses Signal a Cooling in AI's Gas Power Rush
SoftBank reported a massive quarterly loss driven by canceled turbine deposits, highlighting the steep financial risks of over-ordering power equipment for data centers.
🧠AI AnalysisPhoto: TechCrunch AI
Key points
- SoftBank reported a $7.1 billion quarterly loss, with over half tied to power equipment.
- The firm over-ordered turbines by nearly 50% to bypass long manufacturing wait times.
- Experts suggest data center operators are shifting toward grid connections and large batteries instead of exclusive gas reliance.
Japanese investment giant SoftBank has suffered a major financial setback tied to its aggressive push into natural gas infrastructure for artificial intelligence data centers. The firm recently disclosed a $7.1 billion quarterly loss, with more than half of that total resulting from power-generation equipment. Through its SB Energy subsidiary, SoftBank had previously placed massive nonrefundable deposits on over 13 gigawatts of turbines—exceeding its actual requirements by roughly 50%—in an effort to corner the market amidst surging AI electricity demands.
As explained by industry experts, the strategy was designed to leapfrog the multi-year manufacturing queues currently stretching into the early 2030s. However, the gamble faltered as data center operators began reassessing their energy strategies. While natural gas initially served as a reliable fallback against grid delays, experts point out inherent vulnerabilities such as winter supply curtailments. Consequently, operators are increasingly favoring grid connections paired with large-scale battery storage rather than standalone gas plants.
Despite SoftBank writing off over $3 billion in worthless turbine deposits, market analysts note that the broader push for AI energy remains robust. The massive power demands of modern data centers mean that while SoftBank’s miscalculation exposed the ceiling for speculative natural gas procurement, it is unlikely to trigger widespread cancellations across the sector.
What to watch next: Monitor how hyperscalers adjust their long-term power purchase agreements and whether grid-plus-battery configurations replace dedicated fossil fuel plants for new data center builds.
Source TechCrunch AI — techcrunch.com/2026/11/12/softbanks-billion-dollar-loss-may-have-put-a-… ↗
Read next
🏢Big TechGoogle Pixel Tag Performance Limited on Older Android Hardware
Google's new Pixel Tag Bluetooth tracker offers advanced precision features only when paired with devices supporting Bluetooth 6.0 and Android 9.0 or newer.
🚀Startups & FundingFormer Adobe Engineers Launch Phota Labs iOS App to Fix and Enhance Photos Using AI
Backed by a16z, a new iOS application called Phota Labs applies artificial intelligence to upgrade everyday snapshots while maintaining the authentic appearance of subjec…
🔌Chips & HardwareFormer Nvidia CEO Jensen Huang Agrees to Congressional Deposition
Former Nvidia chief executive Jensen Huang will testify privately before U.S. House lawmakers before Thanksgiving following subpoena threats related to national security …
⚖️Regulation & PolicyNintendo Issues Massive GitHub Takedown Targeting Switch Emulators and Mod Chip Firmware
Nintendo has intensified its legal crackdown on piracy tools, filing multiple DMCA notices to remove Switch emulators and over 140 repositories containing mod chip firmwa…
🌐Work & SocietyAWS Introduces Migration Toolkit for Amazon Bedrock Managed Knowledge Base
Amazon Web Services has released a migration guide within its Agent Toolkit to help teams transition from customer-managed to managed knowledge bases on Amazon Bedrock.
🌐Work & SocietyDonald Trump Proposes Former Apple Chief Tim Cook to Lead Nvidia
Following Jensen Huang's resignation, U.S. President Donald Trump has suggested that former Apple CEO Tim Cook take over leadership of Nvidia.